GLP Thanked for Excellence in Service


1 Jun, 2010 - 10:50PM 445

Due to an unexpected internal collapse of Santos Moomba's CO2 Train #6 Regenerator Tower, GLP were called upon to provide the replacement internals at very short notice. In order to get this tower back up & running in the least amount of time, GLP's expert team advised Santos of choosing substitute materials in order to speed up the manufacturing process. GLP ensured that these internals were the very highest priority item in their works.A professionally monitored program was implemented so that the internals would move from the fabricator's floor to Santo site in record time all the while keeping everyone at Santos informed of their progress. It was due to this professionally managed program & the hard work of GLP's dedicated staff that such a large amount of internals could be fabricate & transported to site in less than 6 weeks.